Important update for Garve to Aultguish - from BTO - Broadband Self Digs


The above, under Network 2 - Garve to Aultguish is particularly important to those who are undertaking self digs.

The deadline for completion is Friday 10th August - as outlined in the above schedule:

Activities in Progress 
Surveys and detailed planning – Completed
Spine fibre – Ongoing
Spine build between Inchbae & Aultguish progressing. Traffic management is required along the remaining road to complete the spine.
Local fibre build work – Ongoing
Fibre jointing with spine and local infrastructure has started
Two sites for poling/civils work require discussions with the Forestry Commission – discussions continue
DYO build – ongoing, all customers except the two sites mentioned above now have equipment and know where build to
Network commissioning and auditing – planning started

We plan to start commissioning work in August.  In order for that to happen all DYO’s must be completed by Friday 10th August